Define the unit of work
A staffing discussion becomes easier when everyone agrees what the forecast counts. A contact, case, transaction and resolved customer problem are different units. If a case creates several contacts, multiplying cases by the handling time of one contact understates the work.
Split demand when the work differs materially. Phone calls, asynchronous messages and back-office reviews may need different assumptions. State whether handling time includes follow-up, wrap-up and rework so another planner can reproduce the estimate.
COPC's cited standard treats volume, handling time and shrinkage as forecast inputs, and requires capacity planning to consider channel and target service level. The simple calculation below supports an early planning conversation. It does not cover all those requirements.
Work through an initial estimate
These figures are illustrative. Suppose a team forecasts 1,200 contacts a week at eight minutes per contact. The direct workload is 160 hours: 1,200 multiplied by eight, divided by 60.
A person is paid for 40 hours, but planned shrinkage is 25%. Shrinkage represents paid time unavailable for handling work, such as training, leave and meetings, according to the categories you choose. Available time is therefore 30 hours.
At an assumed occupancy of 80%, those 30 available hours provide 24 workload hours per person. Dividing 160 by 24 gives about 6.7 FTE. Rounding that figure does not produce a finished roster.
| Input or result | Illustrative value |
|---|---|
| Weekly contacts | 1,200 |
| Average handling time | 8 minutes |
| Weekly workload | 160 hours |
| Paid hours per FTE | 40 |
| Shrinkage | 25% |
| Occupancy assumption | 80% |
| Workload estimate | About 6.7 FTE |
FTE = workload hours / [paid hours per FTE x (1 - shrinkage) x occupancy]. Enter shrinkage and occupancy as decimals in this expression. Keep the definitions consistent with your workforce system; organisations can use these labels differently.
Test the assumption that changes the decision
If handling time rises from eight to ten minutes while other inputs stay fixed, weekly workload becomes 200 hours and the estimate becomes about 8.3 FTE. This is a sensitivity check, not a prediction that handling time will increase.
Use plausible scenarios grounded in your own history. Inspect the source of change: a new product, more complex cases, an incomplete knowledge base or a forecast based on an unusually quiet month.
Show the decision maker a range with its assumptions. A precise-looking number can hide a weak demand forecast. A range is more useful when it explains what new evidence would move the staffing decision.
Add the constraints a weekly average misses
Customers do not arrive evenly through the week. A team can have sufficient total hours and still miss its target during a peak. Opening hours, required skills, absence patterns and minimum coverage can all change the roster.
For live channels, use an appropriate queueing or workforce model with interval demand and explicit service targets. For asynchronous work, inspect backlog age, due dates and arrival patterns. Concurrent chats require care because elapsed conversation time and active agent work are different measures.
Separate the steady flow of new work from a plan to clear old backlog. Otherwise a temporary recovery requirement can look like a permanent need, or the backlog can remain hidden inside a staffing number.
Take a better proposal to the review
Bring the demand forecast, the period it covers and the assumptions for handling time, shrinkage and occupancy. Show which assumption has the greatest effect and which operational constraint the simple model omits.
Then state the choice. You may need a better forecast, a schedule change, a knowledge fix or additional capacity. The calculation helps people compare those options. It cannot decide the service target or the acceptable customer wait on their behalf.
Common questions
Can I use an FTE estimate as a roster? No. FTE expresses an amount of work in equivalent full-time hours. A roster must account for coverage, skills, breaks and channel-specific service requirements.
Is 80% occupancy a recommendation? It is an illustrative input in this example. Choose and validate assumptions for your channel and working conditions.